Cambridge City
MA

Policy Order
POR 2018 #19
ORDER ADOPTED
Jan 29, 2018 5:30 PM

That the City Manager is requested to confer with the Commissioner of Public Works and the City Engineer on the potential of utilizing trenchless technology, micro tunneling and/or pipe jacking to lessen the time and impact on the residents of Gore Street.

Information

Department:City Clerk's Office, TTSponsors:Councillor Timothy J. Toomey, Councillor Craig A. Kelley, Councillor Alanna Mallon
Category:Policy Order

Attachments

  1. Printout

Body

WHEREAS:

The sewer installation project on Gore Street can last a duration of at least 9 months; and

 

 

WHEREAS:

Technologies exist that can potentially shorten the time of the project; now therefore be it

 

 

ORDERED:

That the City Manager be and hereby is requested to confer with the Commissioner of Public Works and the City Engineer on the potential of utilizing trenchless technology, micro tunneling and/or pipe jacking to lessen the time and impact on the residents of Gore Street and report back to the City Council.

 

Meeting History

Jan 29, 2018 5:30 PM Video City Council Regular Meeting
draft Draft
RESULT:ORDER ADOPTED